Public construction brings extra requirements: bonds, prevailing wages and strict bid rules. On US federal construction above the threshold in the FAR, performance and payment bonds are required.
What are bid, performance and payment bonds?
The FAR says only separate bid guarantees are acceptable in connection with construction contracts. The chief of the contracting office may waive the requirement when it is not in the government's best interest, for example for overseas construction or emergency acquisitions.
A bond is a guarantee issued by a surety company. Three kinds come up on public construction.
- Bid bond (bid guarantee): submitted with your bid to show you will sign the contract and provide the other bonds if you win.
- Performance bond: protects the government if you fail to finish the work.
- Payment bond: protects subcontractors and suppliers who are owed money.
When are bonds required on US federal jobs?
The Miller Act, now found in 40 U.S.C. chapter 31, subchapter III, requires performance and payment bonds on federal construction contracts exceeding $150,000. This is the figure shown in FAR 28.102-1 as we checked it on 2026-11-14 (FAC 2026-01). Dollar thresholds can be adjusted, so confirm the current number in the FAR.
For contracts above $35,000 and up to $150,000, the contracting officer must choose at least two alternative payment protections instead, such as a payment bond or an irrevocable letter of credit.
Above the threshold, each bond is generally set at 100 percent of the original contract price. The FAR also says bid guarantees are required whenever a performance bond or a performance and payment bond is required.
How do I get bonded?
Bonds come from surety companies, usually through a bonding agent. The surety looks at your finances, experience and work in progress to decide how large a bond it will write for you. Start that conversation well before a bid is due, because it can take time to build a bonding relationship.
What are prevailing wages?
Separately, the Department of Labor notes that for prime contracts over $100,000, the Contract Work Hours and Safety Standards Act requires time-and-a-half pay for hours over 40 in a workweek. Ask whoever prepares your payroll to review both rules before you price labor.
The Davis-Bacon and Related Acts require covered contractors and subcontractors on federally funded construction to pay laborers and mechanics no less than the locally prevailing wages, including fringe benefits. The Department of Labor says the Acts apply to contracts in excess of $2,000 for construction, alteration or repair of public buildings or public works.
The Department of Labor determines the rates, and contracting officers get the wage determination for each contract from SAM.gov. The wage determination is part of the solicitation, so price your labor from it.
Why do site visits matter?
The same provision refers to the clauses on differing site conditions and site investigations. In practice, that means what you could have seen on a visit is generally your risk, so look carefully and write down what you see. Site visits may be arranged through a listed contact during normal duty hours, or the agency may schedule an organized visit with a set date, time and meeting location.
The FAR site visit provision for construction says offerors are urged and expected to inspect the site where the work will be performed. You cannot claim later that you missed something you could have seen.
The solicitation tells you whether visits are by appointment or at a scheduled time, so check the dates early. Take photos and notes, and send questions in writing before the questions deadline.
What is the difference between sealed bids and proposals?
In sealed bidding, bids are opened publicly at the time and place stated in the solicitation. The FAR says award goes to a responsible bidder whose conforming bid is most advantageous to the government, considering price and the price-related factors in the invitation.
In a negotiated procurement, you submit a proposal. A request for proposals must list the evaluation factors and their relative importance, so price may be only one piece of the decision.
Whichever type it is, follow the instructions exactly. For sealed bids, a late bid will not be considered unless a narrow exception in the FAR applies.
Is construction work reserved for small businesses?
Sometimes. The FAR says a contracting officer must set aside an acquisition over the simplified acquisition threshold for small business when offers from at least two responsible small businesses can reasonably be expected at fair market prices. The notice states whether a job is reserved.
If it is, you need to qualify as small for the NAICS code on the notice. SBA assigns a size standard to each NAICS code, based generally on employees or average annual receipts, and publishes a table of them. Bonding capacity is a separate test, so a business can be small and still lack the bonding to take a larger job.
Where do I find construction bids?
Federal construction is posted on SAM.gov, and Canadian federal construction on CanadaBuys. State, county, school and municipal projects use their own sites and their own bond and wage rules. BidTerrier lists open public solicitations and links each one to its official notice.
This is general information, not legal advice. Rules change, so confirm details in the official sources listed below before you bid.
Official sources
- FAR 28.102-1 General (Performance and payment bonds) - acquisition.gov
- FAR 28.102-2 Amount required - acquisition.gov
- FAR 28.101-1 Policy on bid guarantees - acquisition.gov
- Davis-Bacon and Related Acts - U.S. Department of Labor
- FAR 52.236-27 Site Visit (Construction) - acquisition.gov
- FAR 14.101 Elements of sealed bidding - acquisition.gov