A solicitation is long, but you only need to find a few things first: what is wanted, how you will be judged, when it is due and how to submit. Federal solicitations often follow a standard order of sections.

What is a solicitation?

The FAR says a competitive request for proposals must describe the government's requirement, the anticipated contract terms, the information offerors must include in their proposals and the factors and significant subfactors used to evaluate them, with their relative importance. If a document you are reading has none of that, you may be looking at something else, such as a pre-solicitation notice that is not yet the real request.

A solicitation is the government's request for offers. It explains what the agency wants to buy, the rules for competing and how it will choose. A notice on SAM.gov or CanadaBuys is the entry point, and the full package is attached to it.

Read the whole package at least once. Missing a single instruction can make an otherwise good bid unacceptable.

What are the Sections A to M?

Sections K, L and M are the ones bidders most often skim, and they are the ones that decide whether your offer is accepted.

The FAR sets out a uniform contract format with four parts. Not every solicitation uses it, but many negotiated ones do. The sections are:

  • Part I, The Schedule: A is the solicitation or contract form, B is supplies or services and prices, C is the description or statement of work, D is packaging and marking, E is inspection and acceptance, F is deliveries or performance, G is contract administration data, H is special contract requirements.
  • Part II: Section I, contract clauses.
  • Part III: Section J, list of attachments.
  • Part IV: K is representations and certifications, L is instructions, conditions and notices to offerors, M is evaluation factors for award.

What should I do on my first read?

Do a quick pass before the careful one. You are looking for reasons to bid and reasons not to.

  • Find the due date, time and time zone, and the deadline for questions.
  • Read the scope of work and note quantities, frequencies and locations.
  • Check whether the work is reserved, and which NAICS code and size standard apply.
  • Check how you will be judged and how price is treated.
  • List what you must submit: forms, certifications, insurance, references and bonds.
  • Check for attachments such as wage determinations, drawings and pricing sheets, and for amendments that change any of the above.

What do the forms like SF 1449 mean?

Section A is usually a standard form. You will see numbers such as SF 1449, SF 33 or SF 18 on the cover page, and each form number tells you the format the agency chose. These forms typically carry the due date, the contact person and the line items, so start there.

The FAR notes that prescribed forms are not required for every solicitation. When a combined synopsis and solicitation is used, the SF 1449 is not used to issue it, and the notice itself contains the information.

Where is the scope of work?

Look at Section C, the description, specifications or statement of work, and at attachments listed in Section J. This is what you are being asked to do, where, how often and to what standard.

Highlight anything with numbers: quantities, frequencies, response times, hours and dates. Those drive your price.

How will my offer be judged?

The FAR says Section L may tell offerors to organize proposal parts into categories such as administrative, management, technical, past performance, and cost or pricing data. At award, Part IV is kept in the contract file rather than physically included in the contract, but the evaluation factors in Section M still govern how your offer is judged.

Section M lists the significant factors and subfactors the agency will use and their relative importance. The FAR requires a request for proposals to state this. Match your response to those factors, in that order.

Section L gives instructions for preparing your offer, and may require a specific format or separate parts, such as technical, past performance and price volumes. Follow it exactly. Section K asks for the representations and certifications you must complete.

When is it due, and how do I ask questions?

The due date and time appear on the notice and in the form. Note the time zone. Questions have their own earlier deadline, set by the solicitation, and are usually sent in writing to the named contact.

Late submissions are risky. For sealed bids, the FAR says a late bid will not be considered unless a narrow exception applies. Submit early, and check for amendments, because deadlines can change.

How is a Canadian RFP organized?

CanadaBuys says departments set evaluation criteria before issuing the solicitation, tailored to the requirement, and the evaluation plan cannot change after the closing date. Evaluation uses minimum mandatory criteria, point-rated criteria or both. A bid that misses a mandatory item can be set aside, so check each one off.

Canadian federal RFPs do not use the A to M letters, but they generally cover similar ground. Expect a cover page with the closing date, time and zone, instructions on how to submit, the requirement or statement of work, evaluation criteria with mandatory and point-rated items, and the terms of the resulting contract.

A CanadaBuys notice shows a closing date with its time zone, the notice type, and the trade agreements that apply, with the contracting contact named.

BidTerrier lists open public solicitations and links each one to its official notice, so you can read the full package there.

This is general information, not legal advice. Rules change, so confirm details in the official sources listed below before you bid.